HYDRAULICS WINCH PIPE SYSTEM FABRICATION, INSTALLATION, AND TESTING

PT KIAT GLOBAL BATAM SUKSES
Awarded to fabricated, install, and testing of winch for LA BODEUSES dregdging vessel. Location of work at PT Idros Services Batam Indonesia.

Hydraulics system uses of SS316 tubing material and need to chemical cleaning, hydrotest, and flushing to ensure no contamination to the hydraulics oil.

The job will be complete in 2 weeks from the material fabrication, bending, joint, instal, hydrotest, cleaning, and flushing. Estimated manhour consumption is 10000 manhours.